Construction sites during the summer holidays 2018 from FFM Aktuell
20.06.2018 | 06:39 Clock | Service
The summer holidays are often used to carry out important construction work, as the traffic chaos during these weeks is usually limited. Now the road traffic department has informed about traffic-relevant construction measures in the city area starting during the summer holidays. You can find an overview for better planning to avoid and - if possible - bypass the affected areas HERE:
Westend / Nordend
Surface renewal Eschersheimer Landstraße between Hansaallee and Holzhausenstraße
Partial closures, reduction of the roadway to one lane per direction
Construction time: Monday, 9.July, until Sunday, 5.August
Nied
Sewer construction work for the development of a new residential area in the Mainzer Landstraße between Nieder Kirchweg and Nidda
Partial closures, reduction of the roadway to one lane per direction
Construction time: Monday, 25.June, until Saturday, July 14
Fechenheim
New construction of the so-called "Neckermannbrücke" in the Hanauer Landstraße
Ongoing construction work, here: changed traffic routing for the production of the road surface incl. Removal of the temporary ramps
Three full closures in the direction of the city; each from Saturday, 9 p.m., to Monday, 5 a.m.
Planned dates:
1. Saturday, June 30, through Monday, July 2
2. Saturday, July 21, through Monday, July 23
3. Saturday, July 28, through Monday, July 30.July
Construction time: until December
Sachsenhausen-Süd
New construction of the road bridge over the Luderbach in Kennedyallee / corner Richard-Strauß-Allee
Ongoing construction work, here: changed traffic routing in Kennedyallee:
Single lane traffic routing in each direction during the summer holidays +1 week
Construction period: Until November
Airport / Schwanheim
Schwanheimer Bahnstraße between Unterschweinstiege and Schwanheim
Ceiling renewal
Construction under partial closure
Construction time: Monday, 23.July, until Friday, 27.July, 5 p.m.
Construction under full closure
Construction time: Friday, July 27, 6 p.m., to Sunday, 29.July, 24 h
Interstadt
Neue Mainzer Straße
private crane lifting work for an elevated construction
Full closure of Neue Mainzer Straße between Kaiserstraße and Große Gallusstraße
Construction time: Friday, 20.July, 20 o'clock, until Monday, 23.July, 6 o'clock
Westend
Relocation of supply lines in the Senckenberganlage into the city between Robert-Mayer-Strasse and Georg-Voigt-Strasse
Reduction to 2 lanes citybound, the opposite lane is not affected
Construction time: Monday, 25.June, through Friday, 3.August
Deutsche Bahn (DB)
Last S-Bahn tunnel closure in the inner city area
No S-Bahn traffic between Hauptbahnhof and Mühlberg / Südbahnhof
Construction time: Saturday, June 23, to Friday, 3.August
Outlook for some construction sites after the summer holidays until autumn 2018
Gallus.NKleyerstrasse between Sondershausenstrasse and A5 underpass
Renewal of pavements, partial closure of carriageway
Construction period: Monday, 13.August, until November
Gallus / Gutleutviertel
New bridge construction on Camberger Straße between Gutleutstraße and Mainzer Landstraße
Partial closure, establishment of a one-way street in the direction of Mainzer Landstraße
Reroute via Hafentunnel
Construction time: Wednesday, 22.August, until July 2019
Gallus
Mainzer Landstraße towards the city centre between Galluswarte and Hafenstraße
Pavement resurfacing, partial closures in sections
36.51 Traffic site coordination 15.06.2018
Construction period: early October to early November
European Quarter
European Tunnel closures due to maintenance
Time period: Late October/early November
City
Theatre tunnel closures due to maintenance
Timeframe: Tuesday, 30.October, until Thursday, 01.November, in each case from 21 o'clock to 6 o'clock
Altstadt / Sachsenhausen
Lange Straße between Rechneigrabenstraße and Schöne Aussicht as well as Dreieichstraße between Große Rittergasse and Lokalbahnhof
Rehabilitation of the tracks
There are 2 lanes available in each direction
Construction time: Monday, 6.August, until Monday, 20.August, 3 o'clock
Sachsenhausen
Intersection Stresemannallee / Gartenstraße / Theodor-Stern-Kai
Track construction; full closure of the track crossings, lane reduction on the Friedensbrücke
Full closure of left turns from Stresemannallee into Theodor-Stern-Kai; full closure of left turns coming from the direction of Uniklinik from Gartenstraße into Stresemannallee
Construction time: Monday, 1.October, until Monday, 15.October, 5 o'clock
Gallus / Bahnhofsviertel
Niddastraße between Hafenstraße and Taunusanlage relocation of a 110 kV power line
Karlstraße, partial closures
Temporary full closure of Düsseldorfer Straße expected in late 2018 / early 2019
Construction period: (has already started) until February 2019
You can find more current traffic information on the Internet at: http://www.mainziel.de